Work begins on White Settlement Bridge superstructure

Posted June 7, 2018

image of bridge construction site
Estimated construction cost for the three Panther Island bridges is $66 million.

Texas Sterling, the Texas Department of Transportation’s contractor for the Panther Island bridges, has been making major progress on the new White Settlement Bridge.

The eighth and final concrete V-pier pour was completed in May, and the contractor has started constructing the superstructure that will allow for the construction of the deck structure — the part of the bridge motorists will drive on. The contractor is currently working on both the east and west ends of the bridge.

The new bridge will serve as a connector across a new bypass channel and over the Trinity River. The bridge will join its partners at Main Street and Henderson Street as one of Fort Worth’s three iconic V-pier bridges.

The Panther Island project is a collaborative effort between the Trinity River Vision Authority, TxDOT, the City of Fort Worth, North Central Texas Council of Governments, U.S. Army Corps of Engineers and Tarrant County.

View a live cam showing bridge construction.

Get articles like this in your inbox weekly. Subscribe to City News

City News

Calendar

Building Standards Commission Pre-Meeting: 9 a.m. June 25, 2018; City Hall, second floor, Council Conference Room 290, 200 Texas Street.
View the agenda »

Building Standards Commission Meeting: 9:30 a.m. June 25, 2018; City Hall, second floor, Council Chamber, 200 Texas Street.
View the agenda »

Trinity Metro Finance & Audit Committee Working Session: 2:45 p.m. June 25, 2018; Intermodal Transportation Center , 1001 Jones Street, 2nd Floor Community Room.
View the agenda »

Trinity Metro Board of Directors Meeting: 3:30 p.m. June 25, 2018; Intermodal Transportation Center, 1001 Jones Street, 2nd Floor Community Room.
View the agenda »

Harmon Road Improvements Project Meeting: 6 p.m. June 25, 2018; O.A. Peterson Elementary School, 2000 Winter Hawk Drive.

Near Southside Infrastructure Improvements Project Meeting: 6 p.m. June 25, 2018; Broadway Baptist Church, 305 West Broadway Ave.

City Council Work Session: 3 p.m. June 26, 2018; City Hall, Second Floor, Conference Room 290, 200 Texas Street.
View the agenda »

City Council Meeting: 7 p.m. June 26, 2018; City Hall, Second Floor, Council Chambers, 200 Texas Street.
View the agenda »

City Plan Commission Work Session: noon June 27, 2018; City Council Conference Room 290, 2nd Floor, City Hall, 200 Texas Street.
View the agenda »

City Plan Commission Public Hearing: 1:30 p.m. June 27, 2018; Council Chambers, 2nd Floor, City Hall, 200 Texas Street.
View the agenda »

Park & Recreation Advisory Board: 4 p.m. June 27, 2018; Deborah Beggs Moncrief Garden Center, Fort Worth Botanic Garden, 3220 Botanic Garden Boulevard.
View the agenda »

Breakfast at the BAC - This Is One Awesome Sales Guru: 7:30 a.m. June 28, 2018; Business Assistance Center, James E. Guinn Entrepreneurial Campus, 1150 S Freeway.
Register for this event »

Lake Worth Regional Coordination Committee Meeting: 2 p.m. June 28, 2018; Lake Worth Multi-Purpose Center, 7005 Charbonneau Road, Lake Worth, TX, 76135.

Overton Park Drive East Streetlights Project Meeting: 6 p.m. June 28, 2018; Southwest Regional Library, 4001 Library Lane.

Riverside Oakhurst Infrastructure Improvements Project Meeting: 6 p.m. June 28, 2018; Andrew "Doc" Session Community Center, 201 South Sylvania Ave.

View the full city calendar.