Building the foundation of North Main Street's new bridge

Posted March 16, 2018

Archived Content Information and links provided may no longer be accurate.
V-Pier Bridge design
Signature bridges over the future bypass channel are being built now and will allow traffic to enter Panther Island from the north and west.

The recent soggy weather hasn’t dampened progress much on the North Main Street bridge.

Construction on the Trinity River Vision Authority’s third signature V-pier bridge began in late December with traffic detours on North Main Street near Coyote Drive-In and LaGrave Field. The bridge is being built on dry land and will serve as a connector across the new bypass channel. Design of the north end of the bypass channel was approved in December.

Steps in V-pier structure construction

Step 1: Pier shaft construction. This initial step requires drilling approximately 30 feet into the ground to create a strong foundation to support the future bridge structure. Once the pier shafts are drilled, a circular steel cage is inserted in the drilled hole and concrete is poured to reinforce the bridge’s foundation. This bridge will have four pier shafts, each 10 feet in diameter, below ground. Work began on the pier shafts in December and they were completed in early February.

Step 2: Pier column construction. The pier columns are constructed by encasing circular steel reinforcement in high-strength concrete, which connects to the underground pier shafts. The upper part of the pier columns has a round dome that will be visible above the waterline. The four pier columns are underway now; the first two were poured the second week of March.

Step 3: V-pier construction. Once the pier shafts and columns are complete, the bridge’s four signature V-piers will support the bridge’s superstructure, or deck, for vehicle and pedestrian traffic. The North Main bridge will have four V-piers that will consist of approximately 210 cubic yards of steel-reinforced high-strength concrete.

Why a V shape?

The signature bridges get their name from the V-shape of the support pier that will be visible above the water. But there’s more beneath the surface.

The V-shape is an alliance of art and architecture. World-renowned architect Miguel Rosales designed the V-pier structure with Freese and Nichols Inc. of Fort Worth. Aesthetically, the design mirrors structures in Fort Worth’s Cultural District, like the Modern Art Museum. Practically, the V-pier design provides better bridge support with fewer piers. Fewer piers mean less concrete and fewer obstructed views from the river.

Ultimately, the V-piers will support the superstructure of the bridge, which will connect traffic from one side of the bypass channel to the other.

The Panther Island project, which includes three signature bridges positioned along the to-be-realigned Trinity River, are a collaborative effort between the Trinity River Vision Authority, TxDOT, City of Fort Worth, North Central Texas Council of Governments, U.S. Army Corps of Engineers and Tarrant County.

Get articles like this in your inbox weekly. Subscribe to City News

City News

Calendar

City Council Meeting: 7 p.m. March 26, 2019; City Council Chambers, Second Floor, City Hall, 200 Texas Street.
View the agenda »

Metropolitan Area EMS Authority: 10 a.m. March 27, 2019; MedStar Mobile Healthcare, 2900 Alta Mere Drive, Fort Worth, Texas 76116.
View the agenda »

City Plan Commission Work Session: noon March 27, 2019; City Hall, Second Floor, City Council Conference Room 290, 200 Texas Street.
View the agenda »

City Plan Commission Public Hearing: 1:30 p.m. March 27, 2019; City Hall, Second Floor, City Council Chambers, 200 Texas Street.
View the agenda »

Park & Recreation Advisory Board: 4 p.m. March 27, 2019; Fort Worth Botanic Garden, Deborah Beggs Moncrief Garden Center, 3220 Botanic Garden Boulevard, Fort Worth, Texas 76107.
View the agenda »

Bonnie Brae Improvements Project Meeting: 6 p.m. March 27, 2019; Bonnie Brae Elementary, 3504 Kimbo Road.

Tarrant County Adult Education & Literacy Consortium Meeting: 9:30 a.m. March 28, 2019; Workforce Development Board Office, Large Conference Room, 1320 South University Drive, Suite 600.
View the agenda »

Water and Wastewater Capital Improvements Plan Citizens Advisory Committee: noon March 28, 2019; Fort Worth City Credit Union, 2309 Montgomery Street, Fort Worth, Texas 76107.
View the agenda »

Emergency Physicians Advisory Board: 12:30 p.m. March 28, 2019; TCMS Building, 3rd Floor, 555 Hemphill.
View the agenda »

WORKSHOP: Code Compliance 101: 6:30 p.m. March 28, 2019; Northside Community Center, 1100 NW 18th St.

Aviation Advisory Board: 3 p.m. March 29, 2019; Fort Worth Alliance Airport, 2221 Alliance Boulevard, Suite 100.
View the agenda »

Spring Fling at Greenbriar Community Center: 6 p.m. March 29, 2019; Greenbriar Community Center, 5200 Hemphill St.

Community Rummage Sale at Andrew Doc Session Community Center: 8 a.m. March 30, 2019; Andrew Doc Session Community Center, 201 S. Sylvania Ave.

View the full city calendar and current meetings.