Building the foundation of North Main Street's new bridge

Posted March 16, 2018

Archived Content Information and links provided may no longer be accurate.
V-Pier Bridge design
Signature bridges over the future bypass channel are being built now and will allow traffic to enter Panther Island from the north and west.

The recent soggy weather hasn’t dampened progress much on the North Main Street bridge.

Construction on the Trinity River Vision Authority’s third signature V-pier bridge began in late December with traffic detours on North Main Street near Coyote Drive-In and LaGrave Field. The bridge is being built on dry land and will serve as a connector across the new bypass channel. Design of the north end of the bypass channel was approved in December.

Steps in V-pier structure construction

Step 1: Pier shaft construction. This initial step requires drilling approximately 30 feet into the ground to create a strong foundation to support the future bridge structure. Once the pier shafts are drilled, a circular steel cage is inserted in the drilled hole and concrete is poured to reinforce the bridge’s foundation. This bridge will have four pier shafts, each 10 feet in diameter, below ground. Work began on the pier shafts in December and they were completed in early February.

Step 2: Pier column construction. The pier columns are constructed by encasing circular steel reinforcement in high-strength concrete, which connects to the underground pier shafts. The upper part of the pier columns has a round dome that will be visible above the waterline. The four pier columns are underway now; the first two were poured the second week of March.

Step 3: V-pier construction. Once the pier shafts and columns are complete, the bridge’s four signature V-piers will support the bridge’s superstructure, or deck, for vehicle and pedestrian traffic. The North Main bridge will have four V-piers that will consist of approximately 210 cubic yards of steel-reinforced high-strength concrete.

Why a V shape?

The signature bridges get their name from the V-shape of the support pier that will be visible above the water. But there’s more beneath the surface.

The V-shape is an alliance of art and architecture. World-renowned architect Miguel Rosales designed the V-pier structure with Freese and Nichols Inc. of Fort Worth. Aesthetically, the design mirrors structures in Fort Worth’s Cultural District, like the Modern Art Museum. Practically, the V-pier design provides better bridge support with fewer piers. Fewer piers mean less concrete and fewer obstructed views from the river.

Ultimately, the V-piers will support the superstructure of the bridge, which will connect traffic from one side of the bypass channel to the other.

The Panther Island project, which includes three signature bridges positioned along the to-be-realigned Trinity River, are a collaborative effort between the Trinity River Vision Authority, TxDOT, City of Fort Worth, North Central Texas Council of Governments, U.S. Army Corps of Engineers and Tarrant County.

Get articles like this in your inbox weekly. Subscribe to City News

City News

Calendar

Crud Cruiser Mobile Waste Collection: 9 a.m. April 28, 2018; Como Community Center , 4900 Horne St.

Walking Town Hall: 10 a.m. April 28, 2018; Whitley Penn , 1400 W. 7th Street.

Senior Prom: 3 p.m. April 28, 2018; MLK Jr. Community Center, 4216 Avenue M at Miller Ave.

Chisholm Trail Park Nature Education and Bio Blitz Event: 2 p.m. April 29, 2018; Chisholm Trail Park, 4936 McPherson Blvd.

Human Relations Comission Retreat: 9:30 a.m. April 30, 2018; Hazel Harvey Peaec Center for Neighborhoods, Room 201 AB, 818 Missouri Avenue.
View the agenda »

Fort Worth Fire Chief Candidates Community Meet and Greet : 5:30 p.m. April 30, 2018; Bob Bolen Public Safety Complex , 505 W. Felix St Fort Worth, Texas 76115.

Dia de los Niños at Victory Forest Community Center: 6 p.m. April 30, 2018; Victory Forest Community Center, 3427 Hemphill.

Trinity Metro Notice of Public Hearing: 6 p.m. April 30, 2018; Tarrant County College Southeast Campus, North Ballroom, 2100 Southeast Pkwy, Arlington.
View the agenda »

Northside Area Wastewater Improvements Project Meeting: 6:30 p.m. April 30, 2018; Northside Community Center , 1100 NW 18th St.

Legislative and Intergovernmental Affairs Committee: 1 p.m. May 1, 2018; City Hall, Second Floor, City Council Conference Room 290, 200 Texas Street.

Housing and Neighborhood Services Committee: 2 p.m. May 1, 2018; City Hall, Second Floor, City Council Conference Room 290, 200 Texas Street.

City Council Work Session: 3 p.m. May 1, 2018; City Hall, Second Floor, Council Conference Room 290, 200 Texas Street.

Trinity Metro Notice of Public Hearing: 6 p.m. May 1, 2018; Tarrant County College Northeast Campus, NBSS, Room 1103-C, 828 West Harwood Road, Hurst.
View the agenda »

City Council Meeting: 7 p.m. May 1, 2018; City Hall, Second Floor, Council Chambers, 200 Texas Street.

Integrating Communications, Assessment and Tactics Scenario Based Training: 9 a.m. May 2, 2018; Bob Bolen Safety Complex Room 1135, 505 W. Felix Street.
View the agenda »

Facebook Live Town Hall: 12:30 p.m. May 2, 2018; Mayors Facebook page.

Fort Worth Professional Firefighters Association Collective Bargaining Negotiations: 2 p.m. May 2, 2018; IAFF Local Office 440, 3855 Tulsa Way.
View the agenda »

Oakhurst / Riverside Area Wastewater Improvements Project Meeting: 6:30 p.m. May 2, 2018; Riverside Community Center, 3700 E. Belknap St.

View the full city calendar.